But that money could also be applied in other areas of the economy, that might have far better payback. And with France's current track record of nuclear construction, throwing more money at nuclear without fixing the fundamental problems first is serious misallocation of capital.
Just the latest news that is the same as the last decade of bad news:
> EDF now estimates the total cost of the project at 12.7 billion euros ($14.42 billion). Its expected cost has more than quadrupled from the first estimate made in 2004.
https://www.reuters.com/business/energy/edf-announces-new-de...
$15B of lithium ion battery factory would have far far greater carbon impact, dollar for dollar. $1B on early stage startups would similarly be more impactful.