> I am reading prop1A, and it seems to propose that 9.95 billion is enough for a 800-mile railway.
What you linked to is the “argument and rebuttal”, which has…very little information, one way or another (though even there, both the argument for and the argument against clearly indicate that the bond issue is not the whole cost, the former noting “Matching private and federal funding to be identified BEFORE state bond funds are spent”, the latter indicating a potential $90 billion system cost.) The “analysis” has, as one might expect, the actual analysis, including this:
“The authority estimated in 2006 that the total cost to develop and construct the entire high-speed train system would be about $45 billion. While the authority plans to fund the construction of the proposed system with a combination of federal, private, local, and state monies, no funding has yet been provided.”