I’d like to disagree on that one. A single story point shouldn’t be translated to time, but should reflect the relative complexity between tasks (ie. a 7 is harder than a 3 and so on).
You could assign relative complexity based on a number of things:
- number of integrations to other systems, - is the area well known to the team, - is the code well tested, - is CI/CD set up, - do we need a lot of alignment or can we just get started, - etc.
So you’re not estimating time, but complexity or hardness.
Then, supposing you have a stable team, you can go back six months and find out “we do on average 90 points per month” or similar